Evaluasi Penjadwalan Waktu dan Biaya Proyek Penanganan Saluran Drainase Akses Bandara Juanda Kabupaten Sidoarjo dengan Metode Jalur KR

dc.contributor.authorJeni Kartika Rahim
dc.date.accessioned2026-06-18T06:10:57Z
dc.date.issued2025-05-07
dc.descriptionReupload File Repository 17 Juni 2026_Yudi Approved by Teddy
dc.description.abstractThe drainage channel improvement project at the access road to Juanda Airport, Sidoarjo Regency, faced delays and potential cost inefficiencies due to technical and social disturbances, such as public resistance and underground cable obstacles. These issues caused discrepancies between the planned schedule and actual project realization. This study aims to determine the optimal project completion time and cost using the Critical Path Method (CPM), as well as to identify the critical path that affects the overall project duration. Based on the CPM analysis, the project can be completed in 28 weeks, which is 6 weeks faster than the actual implementation duration of 34 weeks. Furthermore, the estimated cost based on the critical path was Rp9,273,693,456, significantly lower than the actual project expenditure of Rp10,948,048,615, indicating potential cost savings of around 15.3%. The analysis also identified two alternative critical paths, with the second path—comprising 13 sequential key activities—chosen for its slightly higher cost efficiency and equal duration. The findings highlight the importance of using structured scheduling methods like CPM in construction project management to enhance time efficiency and cost control, especially in identifying and managing critical activities that directly impact project success.
dc.description.sponsorshipDrs. Eka Bambang Gusminto, M.M. Dr. Intan Nurul Awwaliyah S.E., M.Sc.
dc.identifier.urihttps://repository.unej.ac.id/handle/123456789/9388
dc.language.isoother
dc.publisherFakultas Ekonomi dan Bisnis
dc.subjectCritical Path Method
dc.subjectproject scheduling
dc.subjectproject cost
dc.subjectcritical path
dc.subjectdrainage project
dc.titleEvaluasi Penjadwalan Waktu dan Biaya Proyek Penanganan Saluran Drainase Akses Bandara Juanda Kabupaten Sidoarjo dengan Metode Jalur KR
dc.typeOther

Files

Original bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
JENI KARTIKA RAHIM - 210810201145.pdf
Size:
857.42 KB
Format:
Adobe Portable Document Format

License bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed to upon submission
Description: