Developing Risk Assessment of Push-Back Designs for An Indonesian Coal Mine under Price Uncertainty
Date
2020-07-08Author
SUPARNO, Fanteri
PAITHANKAR, Amol
CHATTERJEE, Snehamoy
Metadata
Show full item recordAbstract
One of the critical jobs in the mine planning and design is to optimize an open pit mine under many uncertain
factors. This paper explains the incorporation process of the volatility of commodity price or market uncertainty into
production phase design and ultimate pit limit using a maximum flow minimum cut algorithm. The Ornstein-Uhlenbeck
(OU) mean-reversion process was used to generate 50-coal price simulations for 10-years ahead. For implementation, data
from an Indonesian coal mining site was integrated into the method and resulted in 42% differences compared to a
conventional way.